Money · July 2026 – June 2027

The town budget

Everyday services · approved yearly budget

This account is called the General Fund. Water, sewer and some other services have separate budgets. Source

Ask OKI about the budget

The short version

More money left over in 2025

The account for everyday town services finished 2025 with $3.83 million more left over than it started with. This includes money moved into the account and other ways the town raised money. Source

Total left in this account: $28,832,956. Some is tied up or needed for other purposes; it is not all cash the town can spend freely. Source
Using savings this year

The town plans to use $3.09 million of money saved from earlier years to help pay for this year’s services. It has not necessarily spent that money yet. Source

The audit found problems2 problems

When the town replaced an old sewer loan with a new one, it did not update its budget or record the change correctly. Source

The auditor accepted the final accounts but flagged these two problems. We have not confirmed whether the town has fixed them. Source

Where the budget goes

23.7%of the General Fund

Fire

Fire protection has the largest department budget shown here—about $24 of every $100 in the General Fund. The fire property-tax line helps fund this service. Source

Budgeted · not payments made

Planned improvements

Source

Explore selected estimates in the five-year capital plan. These are planning figures, not contracts or payments.

What the town is paying back

Loans spread the cost of large purchases over several years. They also add interest. These records explain what the loans bought; they do not establish that the town could not afford to pay upfront.

Wastewater system

Borrowing financed wastewater-system improvements. The 2025 bonds refinanced the earlier 2015 bonds; refinancing replaces existing debt rather than funding a second copy of the project. Source

Repayments are planned in the separate wastewater account. The schedule shows what is due, not payments already made.

Scheduled this year
Amount paying down the loan
Borrowing cost in this payment

● Paying down the loan● Interest · cost of borrowing

See each loan and future payments

2025 refinancing bonds

$3,401,750$2,160,000 paying down the loan + $1,241,750 interest · this year

2017 revenue bonds

$2,778,181$1,940,000 paying down the loan + $838,181 interest · this year

State revolving loan · first allocation

$464,648$436,804 paying down the loan + $27,844 interest · this year

State revolving loan · second allocation

$419,233$380,101 paying down the loan + $39,132 interest · this year

Annual payments ahead

2026–27: $7,063,812

Project costs reported in 2026

Published figures · cost basis varies

Project records updated or checked in 2026, highest cost first. These can be total project costs, not just spending during 2026–27; the source does not consistently identify the cost basis.

July 2024–June 2025 · latest audited year on this site

Last Year's Spending (2025)

What the main services fund spent, compared with its final budget. Explore all 15 spending areas. Water, wastewater and other funds are separate. Source

Final budget
Spent
Below budget overall

Fire

Budget
Spent

$49,566 over budget · 101.3% used Source

What drove the overrun?

Operating costs were $110,901 above budget. Salaries and benefits were $27,805 below budget, and equipment and other major purchases were $33,530 below. Those lower costs partly offset the increase, leaving Fire $49,566 over budget overall. Source

  • Operating costs$110,901 over
  • Salaries & benefits$27,805 below
  • Equipment & other major purchases$33,530 below

This audit schedule does not identify the individual expenses or explain why operating costs rose. We cannot tell from these totals whether the extra spending was avoidable.

These totals leave out money moved between town accounts.
Which expenses went over budget

Some individual lines went over even where the whole department stayed within budget. These amounts overlap; do not add them together.

Fire department total

$49,566 over

Includes operating costs $110,901 above their line budget, partly offset by lower salaries and equipment spending. Source

Police operating costs

$60,366 over

Police stayed $45,837 below its total department budget. Source

Fleet operating costs

$6,761 over

Fleet stayed $450,118 below its total department budget. Source

Transfers to other funds

$5,839 over

Transfers were $5,839 above plan. They are reported separately from the department spending totals above. Source

Loan principal payments

$9,015 over